Location: Santiago, Chile

Client: Echeverría Izquierdo

Technology:

Description: The construction company Echeverría Izquierdo uses ObraLink Control and ObraLink Resistencias in the construction of the Parque Arauco shopping center, reducing the workload for its teams.

Challenge

Solution

Results

  • Continuous and automated monitoring: 13 measurements were taken, with 11 of the 14 points reaching the required tension strength (21 MPa) in under 24 hours. The remaining two did so in under 38 hours, establishing a maximum of 48 hours (see chart).
  • Tensioning time reduction: ObraLink Resistencias technology enabled tensioning up to a third faster than the usual timeframe, improving workflow and reducing excavation delays (see chart).
  • Increased operational efficiency: Automating strength control improved planning accuracy and minimized surprises at the time of tensioning.