Description: Delta uses ObraLink in the construction of 138 apartments in the Agatta Tower. The ObraLink Control modules help them oversee the general contractor's management.
Challenge
Solution
Results
Continuous and automated monitoring: 13 measurements were taken, with 11 of the 14 points reaching the required tension strength (21 MPa) in under 24 hours. The remaining two did so in under 38 hours, establishing a maximum of 48 hours (see chart).
Tensioning time reduction: ObraLink Concrete Strength technology enabled tensioning up to a third faster than the usual timeframe, improving workflow and reducing excavation delays (see chart).
Increased operational efficiency: Automating strength control improved planning accuracy and minimized surprises at the time of tensioning.